As a remedy, she proposed that costs and benefits be reconciled annually rather than netted across the contract’s full duration

Alert Level

Active monitoring. No immediate deadline applies to other operators, but the legal argument Michigan AG Dana Nessel has entered into the public record — that aggregated multi-decade cost accounting can mask ratepayer exposure — is now an active challenge before a state regulator. If the Michigan Public Service Commission grants rehearing and modifies the approved structure, it creates a traceable precedent for how regulators in other jurisdictions assess cost allocation in large data center utility contracts.

What Is Changing

Earlier in October 2026, the Michigan Public Service Commission approved a 20-year electric service contract between DTE Energy and Google for a hyperscale data center in Van Buren Township, near Detroit. The commission’s stated position was that the contract structure ensures no costs are passed to DTE’s other customers.

Nessel filed a petition for rehearing, citing what she described as a “litany of errors” in the commission’s approval. Her core objection is that the contract aggregates electricity costs over the full 20-year term. Under that structure, she argues, below-forecast consumption in any given year — or an early shutdown — could result in other DTE ratepayers effectively subsidizing Google’s facility during that period, even if the aggregate lifecycle math eventually balances. As a remedy, she proposed that costs and benefits be reconciled annually rather than netted across the contract’s full duration. Google did not respond to a request for comment.

Who Is Most Exposed

Operators with active or pending large-load service agreements with investor-owned utilities in regulated states face the most direct exposure. The Van Buren Township case involves a structure that is broadly used: long-term contracts where cost recovery is calculated across the full contract horizon rather than tested year by year. Any operator running a similar arrangement in a state where an AG, consumer advocate, or public utility commission intervenes on ratepayer grounds faces the same line of argument.

Colocation providers serving hyperscale tenants represent a secondary exposure point. If a utility restructures its large-load tariff in response to regulatory pressure — requiring annual true-up mechanisms rather than lifecycle netting — it changes the risk profile of the underlying service agreement and the cost certainty operators have modeled into long-term energy budgets.

Facilities in Michigan’s DTE service territory carry an obvious near-term exposure if the commission grants rehearing and modifies the approved terms. The broader risk is structural: this is the first publicly documented challenge of this type to a hyperscale data center utility contract on ratepayer-subsidy grounds in recent memory, and it is being pursued by a state attorney general rather than an individual intervenor.

What Happens If You Do Not Act

Ignoring this development carries two distinct risks. The first is operational: if annual reconciliation requirements become embedded in future large-load contracts — through modified commission orders or revised tariff filings — operators who have built energy cost forecasts on lifecycle-averaged structures will face unexpected year-over-year variability. The second is strategic: the ratepayer-subsidy framing, if it gains traction in regulatory proceedings in other states, could slow future large-load tariff approvals and increase scrutiny applied to utility-negotiated contracts at the MPSC, MPUC, or equivalent bodies elsewhere. Interconnection timelines are already a primary bottleneck; adding regulatory friction to the tariff approval layer compounds that constraint.

3-Step Action Path

This week: Pull the contract structure underlying any active large-load service agreement your team has negotiated or is currently negotiating with a regulated IOU. Identify whether cost recovery is structured on a lifecycle-aggregate basis or subject to annual true-up. Flag this distinction explicitly in your legal and regulatory review queue.

This month: Engage utility relations managers to assess whether the ratepayer-subsidy argument is likely to surface in any jurisdiction where you have pending large-load tariff applications. Request from utility counterparts whether they anticipate commission or AG intervention in states with active consumer advocacy offices. Consider whether pending contracts should include annual reconciliation provisions proactively, rather than waiting for a regulator to require them.

This quarter: Brief energy procurement and budget teams on the scenario where annual cost reconciliation becomes a standard contract term in regulated states. Model what that structure means for cash flow certainty in years where facility load is below contracted forecast — particularly relevant for campuses that may ramp more slowly than projected due to construction delays or tenant timing. The Michigan case is unresolved, but Nessel’s proposed mechanism is precise enough to model now.

What Is Still Unclear

The Michigan Public Service Commission has not yet ruled on Nessel’s petition for rehearing. Whether the commission will grant rehearing, modify the contract terms, or uphold its original approval is not established. The specific power capacity and load forecast underlying the Google contract have not been reported in available source material, so the precise financial exposure that triggers the ratepayer concern cannot be independently calculated.

Whether other state AGs or utility commissions are watching this proceeding as a template is not confirmed. The ratepayer-subsidy argument has theoretical applicability to any lifecycle-aggregated large-load contract, but whether regulators in other jurisdictions would adopt it depends on each state’s consumer protection framework, the composition of its utility commission, and whether an AG or intervenor chooses to raise it. Because Google has not responded publicly, the counterargument to Nessel’s cost-allocation framing is not part of the public record at this stage.