As the week closes, pJM halted new generation interconnection applications in 2022 to clear a massive backlog and restructure how it evaluates projects

Decision Focus

In late April 2026, PJM Interconnection announced it had received more than 800 new power generation project applications totaling approximately 220 gigawatts of potential capacity — the first major intake cycle since the operator froze its queue in 2022. PJM controls transmission across 13 Midwest and Mid-Atlantic states and serves roughly one in five Americans. It formally reopened submissions after completing a multi-year reform of its interconnection review process. For Global Heads of Data Center Energy with assets or growth plans in the PJM footprint — which includes Northern Virginia, one of the densest data center markets in the world — this is a structural signal on interconnection access, not a routine regulatory update.

90-Second Brief

As the week closes, pJM halted new generation interconnection applications in 2022 to clear a massive backlog and restructure how it evaluates projects. By the end of 2025, it had worked through 170 gigawatts of queued projects, of which approximately 31 percent had received or signed connection agreements. The reformed queue then reopened for a defined intake window, closing in late April 2026 with more than 800 applications representing 220 gigawatts of diverse generation. The urgency is explicit: PJM has acknowledged electricity shortfalls tied to a surge in data center power demand that outpaced new supply additions.

What Is Really Happening?

The surface story is a queue reopening. The underlying story is a grid operator under acute load pressure from AI-driven data center expansion, now attempting to accelerate supply-side response through procedural reform. PJM’s own framing confirms what operators in this market already feel: demand growth from data centers moved faster than the interconnection process could accommodate, creating reliability risk.

The composition of the 800-plus applications is telling. Battery storage leads at 349 projects, followed by natural gas at 157, solar at 142, and wind at 65. There are 45 nuclear projects and 45 solar-storage hybrids. This breakdown reflects an applicant pool that has internalized PJM’s reliability concerns — storage-heavy submissions align with what a capacity-stressed grid operator is more likely to approve and interconnect quickly. The 45 nuclear applications are also notable: whether these represent credible SMR proposals or early-stage speculative filings remains unconfirmed, but their presence at this scale is not routine.

PJM interim CEO David Mills stated explicitly that the operator needs “all the generation we can get” — language that reflects system stress rather than routine procurement.

Why It Matters for Global Heads of Data Center Energy

The queue reopening creates two distinct effects for data center energy strategy in the PJM footprint: a structural loosening of future supply potential, and a near-term acceleration of competition for interconnection priority.

On supply, 220 gigawatts of applications represents significant theoretical headroom. But the 2022–2025 clearance cycle offers a calibration point: of 170 gigawatts processed, only about 31 percent reached agreement. That attrition rate matters when planning against future energy availability. The majority of projects that enter the queue do not complete it, which means sourcing power from developers who hold queue positions requires scrutiny of study status — not just whether a project has applied.

On competition, data center operators are not the only load growth story in PJM’s territory. Industrial electrification and EV infrastructure are adding to demand as well. The reformed queue process may move faster than its predecessor, but 800-plus projects still require sequential study, cost allocation, and utility-level coordination. Queue position and application readiness will continue to determine when power actually reaches the grid — and therefore when it can underpin a PPA or behind-the-meter arrangement.

For teams evaluating new PJM-region site acquisitions or existing site capacity expansions, the question shifts from whether supply is theoretically available to which projects within this new intake cycle are credibly capitalized and positioned to complete interconnection within a planning horizon that matters operationally.

Forward View

Three fronts warrant active monitoring as this queue cycle progresses.

First, study timelines: PJM’s reformed process was designed to reduce review duration, but 800-plus simultaneous applications will test whether those reforms hold under volume. If timelines extend, the 2026 intake class may not deliver interconnected capacity until the early 2030s, widening the near-term supply-demand gap further.

Second, storage project attrition: Battery storage dominates the applicant mix at 349 projects, but storage interconnection economics are sensitive to wholesale market rules, capacity market prices, and curtailment exposure. If PJM’s capacity market signals shift, a portion of these projects may withdraw before completion, materially changing the effective supply outlook.

Third, nuclear project credibility: The 45 nuclear applications are an anomaly by historical standards. If a meaningful share reflects SMR developers with funded programs rather than option-holding, it would represent a genuine shift in PJM’s long-term generation mix — directly relevant to data center operators pursuing long-duration, 24/7 carbon-free offtake.

What Is Still Uncertain

Several material unknowns limit confident planning from this announcement. PJM has not disclosed project-level details for the 800-plus applications, making it impossible to assess which developers have the capital, site control, and permitting status to complete interconnection. The 31 percent agreement rate from the prior cycle is a historical ratio, not a forward guarantee — reformed process mechanics may improve or worsen that outcome. Whether the 45 nuclear applications represent SMR-scale proposals with commercial backing or speculative reservations is unconfirmed. PJM’s study timeline under the reformed process has not yet been tested at this intake volume, and Advanced Energy United’s public statement that the industry is “eager to see” faster study outcomes signals that speed of execution remains an open question, not a confirmed improvement.

One Question for Your Team

Of the developers holding PJM interconnection positions in our target expansion markets, how many have completed the cluster study phase — and which carry queue positions that would survive the 31 percent historical attrition rate under the reformed process?


Sources

  • Energynow — Biggest US Grid Operator to Begin Processing New Power Plant Projects (Link)